The Govt. vide its order dated 6.3.1990 announced the 12.5% Scheme and extended it to all PAPs. In this scheme, the PAP is given back developed land which is 12.5% of the land acquired from him. Out of the 12.5% entitlement, 30% is reserved for social facilities and public utilities. Thus net allotment would be 8.75% of the land acquired from him. The plot allotted to the individual has 1.5 FSI and 15% commercial component permissible on the plot. The PAPs who benefited under the GES Scheme could apply for this scheme as well. The PAP can develop the plot himself or enter into an agreement with the developer for development. The 12.5% Scheme became fully functional in 1994.
CIDCO has earmarked approximately 1064 ha. net land for the 12.5% scheme and has so far disbursed more than 750 ha. land. The disbursal of land was slow till 2005.
In most cases,the flats purchased in Navi Mumbai, are built by builders on something called 12.5% Gaothan expansion scheme and (also called ‘sade barah takka’ plot).In this case the land was initially allotted by CIDCO to a local villager (gaonwalla),in exchange for his farmland,which CIDCO took over.
The exact beneficiary of this scheme is decided by land revenue documents and a document called 7/12 (saat baaraah).These are available with the village Talati,Tehsildar,Patwari,Collector etc.
Basically the ratio of this acqusition was 12.5%,which means that if the villager owned 100 sq meters of farmland,he was allotted 12 meters of land,on which he was free to do construction activity or sell it for a profit.
In such cases,the documents required are…..
Award Copy :-
A type of letter issued by CIDCO,specifying the Name of the villager to whom CIDCO has decided to give 12.5% of the land acquired by it.It is proof that the villager is entitled to a parcel of land from CIDCO.Till this stage,the place and exact spot of allotment is not known to the villager.The only thing he knows is that he will be allotted a specified area of land.
Letter of Intent:-
Once CIDCO is ready to allot the piece of land to the villager holding the award copy,it issues a letter of Intent to the villager telling him the same.He is then shown the exact plot that he will be allotted and his approval obtained via a signature.
Letter of Allotment:-
Once all the approvals of the villager are obtained,a letter of allotment is issued which specifies the villager’s name and exact demarcation of his plot.
Lease Agreement:-
Since CIDCO does not sell any plots (it only gives plots on long term 60 yr lease),it signs a Lease agreement with the villager which specifies the exact terms of the lease.It includes the time limit for constructing the structure,the fines and penalties imposed in case of any violations of the time schedule,transfer charges to be paid to CIDCO and approval of CIDCO incase any new title or interest is created in the property.etc.
Transfer charges:-
After the lease agreement is signed by the villager,he pays the CIDCO transfer charges and other CIDCO charges.
Tripartite Agreement:-
This is a type of agreement by which the villager transfers his rights,title and interest on the land to a third party,namely,the builder/developer/construction company.This could be done for various reasons including lack of funds,expertise etc.Transfer charges are paid to CIDCO and CIDCO now admits the builder/developer/construction company in its records as the owner of the land.
Final Order:-
Its a letter issued by CIDCO stating conclusively that the rights title and interest of the said plot now belong to the builder and not the villager.
Once these documents are in place,the builder takes over and starts the procedures to construct the building.This involves getting permissions from various agencies like CIDCO and NMMC,Fire dept etc.
After completion,the builder/developer obtains the Occupancy Certificate.
Only after obtaining the Occupancy Certificate only can the builder sign the lease deed with CIDCO.
This lease deed is the most important document that a flat buyer should insist on,once the Occupancy certificate is issued to the building.
Society formation,Conveyence of land in favour of the society etc will become all the more difficult if this document is not available.
Check If LOAN is possible from nationalized bank.
If....YES......Its Legal Plot
If.....No.......its illLegal Plot.
DOCUMENTS to be checked while Buying Such PLOTS :-
1.Occupancy Certificate
2.Commencement Certificate.
3.Tripartite Agreement [ Land Owner, Cidco & Developer]
4.NOC from Cidco
5.Transfer Of Title
6.Registered Sale Agreement.
7.Property Tax on your Name.
8.Society Registered / Formed
9.Completion Certificate.